Question: A project team member working on stakeholder analysis seeks clarity on what is considered to be a stakeholder. When considering stakeholder and communication for agile
A project team member working on stakeholder analysis seeks clarity on what is considered to be a stakeholder. When considering stakeholder and communication for agile project, how do you identify stakeholders?
a Consult the project plan for who be may influence the project.
b Ask who may use, be affected by or influence the project.
c At the scrum meeting, document who will influence the project.
d Ask the scrum master for a copy of the stakeholder matrix