Question: A project that exceeds its original budget and time estimates most likely suffers from which of the following? A ) scope expansion B ) scope
A project that exceeds its original budget and time estimates most likely suffers from which of the following?
A scope expansion
B scope definition
C scope mismanagement
D scope creep