Question: A project that is in progress requires a resource with a specialized skill. Because of time limitations, the agile team has two options: either borrow
A project that is in progress requires a resource with a specialized skill. Because of time limitations, the agile team has two options: either borrow a team member from another department who can work part time or use an independent contractor. The eight team members discuss the options, but they are unable to reach an agreement. The vote is 50/50, and both options have positive benefits as well as risks. What should the team do? Group of answer choices Ask the product owner to decide. Empower the team lead to make a decision based on multicriteria analysis. Wait until the next retrospective and ask again. Use Roman voting