Question: A project using a hybrid approach to migrate from a current system to a new and enhanced systom is underway. The plan is to migrate
A project using a hybrid approach to migrate from a current system to a new and enhanced systom is underway. The plan is to migrate the system in stages However, the operations team is complaining that they are not ready to start supporling the new system How should the project manager effectively approach this situation? O Prepare dotated documentation to be shared with the operations loam during project closure. Change the projact management plan to add a final stage for product handoft to the operations team Include knowledge transfer sessions between the project and operations teams al every stage. Create a lessons learned register to include operations team training for future projects