Question: . A project was expected to be completed in 1 2 weeks by a crew of 6 workers. The work was to be completed without
A project was expected to be completed in weeks by a crew of workers. The
work was to be completed without overtime, working hour workweeks. Workers
were to be paid $ per hour, including all fringes. However, before construction
began, the owner decided that the project schedule would be accelerated by having
the workers work hours on Saturdays, with wages paid timeandahalf on
Saturdays