Question: A project was planned using PERT with three time estimates. The expected completion time of the project was determined to be 4 0 weeks. The
A project was planned using PERT with three time estimates. The expected completion time of the project was determined to be weeks. The variance of the critical path is What is the probability that the project will be finished in weeks or less? Point O None of the alternatives
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
