Question: A project will be using a company to provide technicians for a distribution centerproject. Presently the Project Manager is in contract negotiation with a vendor

A project will be using a company to provide technicians for a distribution centerproject. Presently the Project Manager is in contract negotiation with a vendor and the negotiations are going too smooth. In what process is the Project Manager Involved?

Seller selection in procurement planning

Plan Purchases and Acquisitions

Seller selection in procurement conducting

Request Seller Responses