Question: A project will cost Rs 50,000 today. It is expected to generate cash flows of Rs 30,000, Rs 25,000 and Rs 15,000 each year through
A project will cost Rs 50,000 today. It is expected to generate cash flows of Rs 30,000, Rs 25,000 and Rs 15,000 each year through year 1 to 3. The discount rate is 18 percent. Calculate the project's Net Present Value (NPV) and Internal Rate of Return (IRR). (without excel)
Year Cash Flow (Rs) 0
0 C0 -50000
1 C1 30000
2 C2 25000
3 C3 15000