Question: A project with 7 activities is shown below. A STA F FIN The duration of activities A, B, C, and Dare 22, 31, 14, and

A project with 7 activities is shown below. A STA
A project with 7 activities is shown below. A STA F FIN The duration of activities A, B, C, and Dare 22, 31, 14, and 24 days, respectively. On the other hand, the duration of activities E, F, and G are 25, 30, and 22 days. Assuming the project starts at the end of day 0, the earliest finish time of activity will be at the end of day