Question: A project with a Budget at Completion ( BAC ) of $ 1 , 0 0 0 , 0 0 0 is 6 0 %

A project with a Budget at Completion (BAC) of $1,000,000 is 60% complete with an Actual Cost (AC) of $700,000 and an Earned Value (EV) of $800,000. What is the Estimate at Completion (EAC) if the CPI and SPI are assumed to remain constant?
$1,200,000
$1,100,000
$1,150,000
$900,000