Question: A project with five activities is planned with a budget of $10,000 and project duration of 5 months. Its master schedule is given below. Month

A project with five activities is planned with a

A project with five activities is planned with a

A project with five activities is planned with a

A project with five activities is planned with a budget of $10,000 and project duration of 5 months. Its master schedule is given below. Month 5 Activity . 000D Budget ($) Month 1 Month 2 Month 3 Month 4 2,000 Scheduled 2,000 Scheduled 2,000 Scheduled 2,000 Scheduled 2,000 D E Scheduled After two months, actual progress of the project is measured and reported as follows. Activity A is 80% complete and the total actual cost is $1,800 Activity B is 100% complete and the total actual cost is $1,800 Activity C is 90% complete and the cost to date is $2,000 16. (4 points) Using the Earned Value Method, what is the planned value? a. 24. (4 points) All activities in a project took 10% longer time than their baseline schedule. What is the schedule variance at completion

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!