Question: A project with seven activities has been defined in the following table. a) Draw network diagram in excel. b) Show the critical path on the
A project with seven activities has been defined in the following table.
a) Draw network diagram in excel.
b) Show the critical path on the network diagram.
| No | Activity | Predecessors | Week |
| 1 | A | ---- | 6 |
| 2 | B | ---- | 7 |
| 3 | C | A | 5 |
| 4 | D | B,C | 6 |
| 5 | E | B,C | 5 |
| 6 | F | D | 8 |
| 7 | G | E,F | 4 |