Question: A project with seven activities includes only four paths that are shown below along with their lengths. The following table provides the opportunities for crashing
A project with seven activities includes only four paths that are shown below along with their
lengths. The following table provides the opportunities for crashing activities.
Suppose each day of shortening crashing the project saves $ Determine how many days the
project can be crashed, and report the total cost for this crashing and how long the project will take
to complete after the crashing. Show all your work, including the activity or activities crashed
in each step and their cost.
Cost for crashing
How long is the project after crashing?