Question: A project you manage is expected to be completed in 16 months at a monthly cost of $20,000. The project is 60% completed after 4
A project you manage is expected to be completed in 16 months at a monthly cost of $20,000. The project is 60% completed after 4 months at a cost of $80,000.
Calculate the estimated cost to complete the project.