Question: A project's budget at completion (BAC) is $400,000 with a CPI of 0.5. If the past performance of the project reflects the future performance, what

A project's budget at completion (BAC) is $400,000 with a CPI of 0.5. If the past performance of the project reflects the future performance, what is the project's EAC? a $2,000,000 b $800,000 c $100,000 d $200,000