Question: A project's net present value is increased if Question 20 options: 1-the CCA rate is decreased. 2-the rate of inflation rises. 3-the CCA rate is
A project's net present value is increased if
Question 20 options:
1-the CCA rate is decreased.
2-the rate of inflation rises.
3-the CCA rate is increased.
4-the discount rate is increased.
5-the company's net income is negative during the life of the project.
Question 19 (1 point)
Cost analysis has two dimensions, which are
Question 19 options:
| 1- | project and time. | ||||||||||||||||||||||||||||||
| 2- | project and non-financial. | ||||||||||||||||||||||||||||||
| 3- | present and the future. | ||||||||||||||||||||||||||||||
| 4- | project and financial. | ||||||||||||||||||||||||||||||
| 5- | financial and non-financial. Question 18 (1 point)
A comparison of year-to-year changes in customer net present value estimates Question 18 options:
|
Step by Step Solution