Question: A projects scope has undergone continuous growth which negatively impacts its schedule and cost. What should the project manager have done better to minimize these
A projects scope has undergone continuous growth which negatively impacts its schedule and cost. What should the project manager have done better to minimize these impacts?
A. Developed a change management plan
B. Requested project sponsor approval
C. Improved communications
D. Assessed project requirements to establish project deliverables