Question: A) Proton's Car sales are listed below. Develop a three-week moving average. (5 Marks) Week Proton Sales 1 27 2 55 3 13 4 19
A) Proton's Car sales are listed below. Develop a three-week moving average. (5 Marks)
| Week | Proton Sales |
| 1 | 27 |
| 2 | 55 |
| 3 | 13 |
| 4 | 19 |
| 5 | 21 |
| 6 | 33 |
| 7 | - |
B) Briefly explain the main tasks of the project manager. Elaborate the measures that should be taken for product development (5 Marks)
C) The firm is having a product with an annual Demand = 350, the cost of Holding per year = RM100 per unit, and the Order cost = Rm99 per order, the company is operating 250 working days per year
1- Calculate the Economic Order Quantity (EOQ). (3 Marks)
2- How many orders should be processed per year? (2 Marks)
3- What is the expected time between orders? (2 Marks)
4- Calculate the total cost of the inventory policy. (3 Marks)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts