Question: A quality assurance engineer computed the following values for p-chart Sample size =100 p. bar =0.002 Upper Control Limi =0.08368 Lower Control Lmit =0,02168 During

A quality assurance engineer computed the following values for p-chart Sample size =100 p. bar =0.002 Upper Control Limi =0.08368 Lower Control Lmit =0,02168 During a given day, suppose a sample of 100 bulbs was selected tiom the machine and that 14 were found delective. If the supervisor decided to shit the machine to lacate the taut, which statement below will be correct. Select one: a. One sample is not enough to reach any conclusion b. The decision to shut the machine was correct c. Type-2 error may be commtied d. Type-1 error may be commtied