Question: A question on optimising a three task project using methods of compressing the project schedule. Methods of compressing the project schedule. When resources are not

A question on optimising a three task project using methods of compressing the project schedule. Methods of compressing the project schedule. When resources are not constrained, we can change the way resources are applied (crashing) by: relieving employees of other responsibilities to allow them to devote more hours each day to the project reallocating resources from non-critical activities to provide the extra help you need adding resources - additional staff, overtime, additional equipment, vendor incentives to complete sooner, or even outsourcing components of the work. Dig trench 15 - Pipe laying 12 - Fill 6 What are the different ways in which you could optimise this three-task project, to reduce it's 33 day duration? What are the assumptions you are making in doing so?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!