Question: A ranking conflict that occurs when evaluating two mutually exclusive projects using the NPV technique and the IRR technique can be resolved by _____. a.
A ranking conflict that occurs when evaluating two mutually exclusive projects using the NPV technique and the IRR technique can be resolved by _____. a. using the modified internal rate of return (MIRR) method b. using traditional payback period method c. using the profitability index method d. using the internal rate of return (IRR) method e. using discounted payback period method