Question: A real estate developer contracts an architecture firm to create plans for a new building by a specific deadtline. Before the deadine, the architects took
A real estate developer contracts an architecture firm to create plans for a new building by a specific deadtline. Before the deadine, the architects took actions that made it impossible to meet the deadline by halting all work on the first project and committing all their resources to a new project with a different developer.They have not yet breached the contract, so the developer does not yet have a claim that has ripened into a cause of action.This appears to be a condition precedent to performance by the architects.This appears to be a condition subsequent to performance by the architects.This likely constitutes an anticipatory breach of the contract.