Question: A real estate developer will build a small office complex in Montreal. The project has a total budget of $1,300,000 including interest estimated at $15,000.

A real estate developer will build a small office complex in Montreal. The project has a total budget of $1,300,000 including interest estimated at $15,000. The expected cash flows are as follows (assume each cash flow occurs at the end of the quarter):

Quarter 1: Land purchase: $200,000

Soft costs: $100,000

Hard costs: $200,000

Quarter 2: Soft costs: $100,000

Hard costs: $200,000

Quarter 3: Hard costs: $185,000

Quarter 4: Hard costs: $300,000

The lender is willing to provide a construction loan with a maximum LTC of 70% including interest. The interest rate is expected to be 5% per year throughout the development process and will be capitalized quarterly.

a) What is the construction loan balance at the end of Quarter 4?

B) If the stabilized NOI at the end of Quarter 4 is $120,000 and comparable cap rates are 8%, calculate the amount the equity investors could withdraw from the project if they secure a 5-year mortgage with an interest rate of 5%, an amortization period of 15 years, a maximum LTV of 75% and a minimum DSCR of 1.25.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!