Question: A recent project experienced a similar activity taking 1 2 days to complete. The team now has more experience and can do the work more
A recent project experienced a similar activity taking days to complete. The team now has more experience and can do the work more efficiently, therefore it is estimated at days duration This is an example of:
Group of answer choices
Analogous Estimating
Monte Carlo Technique
Parametric Estimating
Parkinson's Law