Question: A recent project included 2 , 0 1 5 square feet of sus - pended acoustical ceiling. It took 2 6 labor hours to complete

A recent project included 2,015 square feet of sus-
pended acoustical ceiling. It took 26 labor hours to
complete the ceiling. Determine the productivity in
labor hours per square foot based on this historical
data.