Question: A repetitive wiring activity is required for your building project. There are a total of 40 iterations of this wiring activity required for the building
A repetitive wiring activity is required for your building project. There are a total of 40 iterations of this wiring activity required for the building project. The first iteration of the wiring activity took 9.5 hours and the learning rate is 66%. Assuming 19 iterations are required to achieve the steady state rate, calculate the steady state rate for the wiring task.