Question: A resource - constrained project is one that assumes that the level of resources available cannot be exceeded. We learn that the Impala Platinum case

A resource-constrained project is one that assumes that the level of resources available cannot be exceeded. We learn that the Impala Platinum case study project had resource constraints. Refer to the following Impacts of Resource-constrained Scheduling, and contextualise the theory to the case study project-showing how the case study project could have benefited if this theory was adopted, and provide an analogy between the Impala Platinum case study and the Department of agriculture project of providing new agricultural infrastructure for the local farmers in the community:
1. Reduces slack
2. Reduces flexibility by using slack to ensure delay is minimized
3. Increases the number of critical and near critical activities
4. Scheduling complexity increases due to resource constraints being added to
5. Technical constraints.
6. Start times may now have two constraints
7. The traditional critical path concept of sequential activities is no longer valid as the resource constraints can break the sequence and leave the network with a set of disjointed critical activities.
8. Parallel activities can become sequential
9. Activities with slack on a time-constrained network can change from critical to non-critical.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!