Question: A resource - constrained project is one that assumes that the level of resources available cannot be exceeded. We learn that the Impala Platinum case
A resourceconstrained project is one that assumes that the level of resources available cannot be exceeded. We learn that the Impala Platinum case study project had resource constraints. Refer to the following Impacts of Resourceconstrained Scheduling, and contextualise the theory to the case study projectshowing how the case study project could have benefited if this theory was adopted, and provide an analogy between the Impala Platinum case study and the Department of agriculture project of providing new agricultural infrastructure for the local farmers in the community:
Reduces slack
Reduces flexibility by using slack to ensure delay is minimized
Increases the number of critical and near critical activities
Scheduling complexity increases due to resource constraints being added to
Technical constraints.
Start times may now have two constraints
The traditional critical path concept of sequential activities is no longer valid as the resource constraints can break the sequence and leave the network with a set of disjointed critical activities.
Parallel activities can become sequential
Activities with slack on a timeconstrained network can change from critical to noncritical.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock