Question: a ) Rich's managers would like to determine the total project completion time ( in days ) and those activities that lie along the critical
a Rich's managers would like to determine the total project completion timein days and those activities that lie along the critical path.
Part
To find the expected activity time of an activity, the beta distribution weights the three time estimates as follows: