Question: A Risk Burndown Chart is calculated using which formula? Question 6 options: a) Size of loss in days x Probability of risk occurring = Exposure
A Risk Burndown Chart is calculated using which formula?
Question 6 options:
|
|
|
| a) | Size of loss in days x Probability of risk occurring = Exposure |
|
|
|
| b) | Exposure x Probability of risk occurring = Size of loss in days |
|
|
|
| c) | Size of loss in days - Probability of risk occurring = Exposure |
|
|
|
| d) | Size of loss in days + probability of risk occurring = Exposure |
Question 7 (12.5 points)
True or false: Scrum uses a defined process control for project management.
Question 7 options:
| a) True | |
| b) False |
Question 8 (12.5 points)
Scrum is built to manage risk, relying on which development approaches? Select all that apply.
Question 8 options:
|
|
|
| a) | Adaptive |
|
|
|
| b) | Iterative |
|
|
|
| c) | Incremental |
|
|
|
| d) | Complex |