Question: A risk has been identified in the first iteration. It's expected monetary value is projected at $45,000, and the value of the first feature is
A risk has been identified in the first iteration. It's expected monetary value is projected at $45,000, and the value of the first feature is $23,000. If the risk can't be mitigated effectively and for less money, what could occur on the project?This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option.%0D%0Aoption%0D%0AA%0D%0A%0D%0AA risk meeting to determine what to do next.%0D%0Aoption%0D%0AB%0D%0A%0D%0AUpdate the risk-adjusted backlog to handle the risk before building the feature.%0D%0Aoption%0D%0AC%0D%0A%0D%0AThe project may reach fast failure.%0D%0Aoption%0D%0AD%0D%0A%0D%0ADetermine solutions in the sprint planning meeting