Question: A road - paving crew required 1 4 hours to repave a 5 mile stretch of road, using $ 2 , 0 0 0 in

A road-paving crew required 14 hours to repave a 5 mile stretch of road, using $2,000 in materials. The crew consisted of four workers who each earn $20 an hour. Calculate a multifactor estimate of productivity for this crew.
A.0.000001603 miles of road per dollar
B.0.0001603 miles of road per dollar
C.0.00001603 miles of road per dollar
D.0.001603 miles of road per dollar