Question: A schedule is said to be resource-constrained. If so, all of the following consequences become evident to the project manager during execution , except for?
A schedule is said to be "resource-constrained". If so, all of the following consequences become evident to the project manager during execution, except for?
The present network duration cannot be met due to lack of resources.
Rolled up cost of the project is more than the total cost allowed in the project scope.
The resources are over committed by having been assignedto more than onemore activity concurrently.
The scope must be reduced.