Question: A schedule update is: (2 Points) A schedule with resources and budget A schedule that reflects new design modifications A revised schedule reflecting project information
A schedule update is: (2 Points) A schedule with resources and budget A schedule that reflects new design modifications A revised schedule reflecting project information at a given data date regarding completed activities, in-progress activities, and changes in future work