Question: A senior decision maker on your project has recently left your organization and is no longer impacted by the project, nor will they have any
A senior decision maker on your project has recently left your organization and is no longer impacted by the project, nor will they have any influence on the project. What should you do next?
A Update the risk register because this person was a key decision maker.
B Notify the team.
C Reach out to their replacement.
D Update the stakeholder register to identify this person as a nonstakeholder.