Question: A serial process has 5 steps A (4), B(5), C(2), D(6), and E(3) that have to be performed in this order. The numbers in parentheses

A serial process has 5 steps A (4), B(5), C(2), D(6), and E(3) that have to be performed in this order. The numbers in parentheses are the times (in minutes) needed to process a unit. For each unit produced by this process, the process has a total idle time of:

Group of answer choices

10 mins

6 mins

3 mins

1 min