Question: A) Setup cost B) Setup Time Rick Wing has a repetitive manufacturing plant producing automobile steering wheels. Use the following data to prepare for a

A) Setup cost
B) Setup Time
Rick Wing has a repetitive manufacturing plant producing automobile steering wheels. Use the following data to prepare for a reduced lot size. The firm uses a work year of 295 days. Setup labor cost $60.00 per hour Annual holding cost $10 per unit Daily production (8 hours) 800 units/day Annual demand for steering wheels 30,975 (295 days x daily demand of 105 units) Desired lot size (2 hours of production) Q = 200 units a) Setup cost = $ (round your response to two decimal places)Step by Step Solution