Question: a sevw 5-53 A subdivision developer must construct treatment plant and deposit sufficient money in a perpetual trust fund to pay the $5000 per yeat
a sevw 5-53 A subdivision developer must construct treatment plant and deposit sufficient money in a perpetual trust fund to pay the $5000 per yeat operating cost and to replace the treatment plant every 40 years. The plant and future replacement plants will cost $150,000 each. If the trust fund earns 8% interest, what is the developer's capitalized cost