Question: A shift needs to be planned considering the following conditions and current kpi realizations. What actions would you take? - You are on the 2

A shift needs to be planned considering the following conditions and current kpi realizations. What actions would you take?
- You are on the 21st day of the month.
- The planned workload of 60 k is as in the table below.
- Each team member can do one unit of work in 50 s. The unit time required for each type of work will be assumed to be equal. The shift involves 7 hours of work, excluding breaks.
- At the start of the shift, you find out that 25% of your team of 100 is missing due to absenteeism.