Question: A significant difference between the CPM Project network and the PERT network is: The PERT method enables calculation of expected project completion based on task

A significant difference between the CPM Project network and the PERT network is:
The PERT method enables calculation of expected project completion based on
task variation; The CPM method does not allow for task variation nor expected
project completion.
The CPM network accounts for task and project variation; PERT allows for task
variation but does not provide a way to consider project variation.
The CPM method enables calculation of expected project completion based on task
variation; while PERT does not provide a way to consider task variation.
 A significant difference between the CPM Project network and the PERT

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!