Question: A simple CPM network has three activities, A , B , and C . A is an immediate predecessor of B and of C .
A simple CPM network has three activities, A B and C A is an immediate predecessor of B and of C B is an immediate predecessor of The activity durations are
a The critical path is ABC duration
b The critical path cannot be determined without knowhg PERT expected activity times.
c The network has no critical path.
d The critical path is ABC duration
e The critical path is AC duration
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock