Question: A simple CPM network has three activities, A , B , and C . A is an immediate predecessor of B and of C .

A simple CPM network has three activities, A, B, and C.A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4,B=4,C=5.
 A simple CPM network has three activities, A, B, and C.A