Question: A simple CPM network has three activities, A , B , and C . A is an immediate predecessor of B and of C .

A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C.B is an immediate predecessor of C. The activity durations are A=5,B=7,C=6.
The network has no critical path.
The critical path is A-C, duration 11.
The critical path is A-B-C, duration 18.
The critical path cannot be determined without knowing PERT expected activity times.
The critical path is A-B, duration 12.