Question: A simple CPM network has three activities, A , B , and C . A is an immediate predecessor of B and of C .

A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=8.
A.
The critical path is A-B-C, duration 13.5
B.
The network has no critical path
C.
The critical path is A-B-C, duration 15.
D.
The critical path is A-C, duration 12.
E.
The critical path cannot be determined without knowing PERT expected activity times.