Question: A simple CPM network has three activities, A , B , and C . A is an immediate predecessor of B and of C .
A simple CPM network has three activities, A B and C A is an immediate predecessor of B and of C B is an immediate predecessor of C The activity durations are A B C
A
The critical path is ABC duration
B
The network has no critical path
C
The critical path is ABC duration
D
The critical path is AC duration
E
The critical path cannot be determined without knowing PERT expected activity times.