Question: A simple CPM network has three activities, A , B , and C . A is an immediate predecessor of B and of C .

A simple CPM network has three activities, A, B, and C.A is an immediate predecessor of B and of C.B is an immediate predecessor of C. The activity durations are A=4,B=3,C=8.
Select one:
a. The critical path is A-B-C, duration 15.
b. The network has no critical path.
c. The critical path is A-C, duration 12.
d. The critical path is A-B-C, duration 13.5