Question: A simple CPM network has three activities, A , B , and C . A is an immediate predecessor of B and of C .

A simple CPM network has three activities, A,B, and C.A is an immediate predecessor of B and of C.B is an
immediate predecessor of C. The activity durations are A=4,B=3,C=5.
A. The critical path is A-C, duration 10.5
B. The network has no critical path.
C. The critical path is A-B-C, duration 12.
D. The critical path is A-B-C, duration 9.
E. The critical path cannot be determined without knowing PERT expected activity times.
 A simple CPM network has three activities, A,B, and C.A is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!