Question: A simple project has 5 activities. The project is not complete until all of the activities are completed. Use the table below to draw the

A simple project has 5 activities. The project is

A simple project has 5 activities. The project is not complete until all of the activities are completed. Use the table below to draw the process flow diagram to the right. Use the EST - EFT convention to find the process flow time. Show your work. Activ Pred Activity Time (min) A 2 B A 9 A 3 D 7 E B.D 4 What is the critical path for the process above? Critical Path= What is the project completion time for the scenario above? T= #N/A

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!