Question: A single layer building engineering has 5 construction sections and 4 professional teams ( A , B , C and D ) . Flow rhythms

A single layer building engineering has 5 construction sections and 4 professional teams (A, B, C and D). Flow rhythms are listed in Table 1. There is 2 days organization pause after team B is completed. Try to organize a No rhythm Flow Construction and drawing the construction schedule. The continuous working must be provided for each professional team.
Table 1 Flow rhythms of each professional team on construction sections