Question: A single layer building project has three construction progress ( A , B C ) with flow rhythms of 5 , 1 5 and 1
A single layer building project has three construction progress with
flow rhythms of and days. There is technical pause after process
is completed. points
Questions:
Calculate the construction period based on Multiple rhythm flow
construction principle.
Draw the construction schedule in the blank schedule chart.