Question: A Six Sigma project has reduced the variability in a process. What should be done to facilitate further reductions in variability? Answers A . Perform
A Six Sigma project has reduced the variability in a process. What should be done to facilitate further reductions in variability?
Answers
A
Perform a failure modes and effects analysis.
B
Hold a brainstorming session.
C
Perform a measurement system capability reanalysis.
D
Develop a control plan.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock