Question: A small project involves 11 activities and their time estimates are listed in the following table. All durations are in days. (a) Draw the project


A small project involves 11 activities and their time estimates are listed in the following table. All durations are in days. (a) Draw the project network and find the critical path. (a) Draw the project network and find the critical path. (b) Find the total slack and free slack for non-critical activities (c) What is the probability that the project will be completed in 40 days? [4+3+3=10]